Bye bye big city!

The 2025 Calendars are HERE. Two different editions, two different sizes, and a digital package!! Starting at $12.97US
Me? OCD?? Nah, it wasn't so much a case of being obsessive as it was an understanding of how the local building and construction inspectors think and what they want to see. For trenches, they typically drop a tape and see how deep the trench is. Most trenches are dug to be deep in the middle and shallower along the walls; that is a function of the shape of the tools, shovels et al, that are used. Obviously a baby back hoe or similar would deliver a hole or trench that is more square but in my back yard there was no access for such luxuries so it was hand bomb all the way. Making the trench floor square to the walls also made it a consistent depth from side to side. So, no matter where the inspector dropped that tape, he/she would get the same measurement +/_ and it would be deeper than code minimum wanted. In that situation the inspector really has no valid reason to disprove the work. First inspection approval means the work moves along and keeps the costs down. A inspection rejection means the work has to be redone and then another inspection scheduled. That puts you way down on the schedule since second visits come after the first visits are done; and why the contractors are so picky about the work that the laborers do. Since I was my own contractor, I had to be picky about my work 'cause I had no one to blame but Moi if it didn't get done to spec and make the grade/pass.


Just me trying to dot the "i's" and cross all the "t's" completely the first time. Summer's are only 10 weeks long around here and I wanted at least to have the shell built and hoarded in by fall. As it turned out,it was the day before Christmas when the door guys finally showed up and hung the main door!!
 
  • Like
Reactions: Texas82GP
Quick update. Second floor framing and roof framing is complete....

IMG_20240907_165225.jpg

IMG_20240907_165227.jpg

IMG_20240907_165201.jpg


Next week they will work on roof decking, exterior sheathing and framing for the soffits and fascia.

The barn is skinned...

IMG_20240907_165214.jpg

IMG_20240907_165219.jpg

20240905_145520.jpg


Next for the barn will be forming and pouring the slab. That's all for now friends.
 
I assume the lack of updates over the last 2 months means you've just been busy moving in, right?
No, that's just the fastest two months of my life. The barn doesn't look much different. I was probably waiting until the slab got poured but the house has been going full speed ahead.
1. Framing is done
2. The roof is decked
3. The cornicing is done
4. All windows and doors are installed
5. The plumbing/electrical/HVAC rough in is done
6. The roof is mostly shingled
7. The brick and stone is mostly done
8. The spray foam insulation has gone in
9. Sheetrock was being installed last Saturday, which was the last time I was out there
10. The power pole for our drop service has been installed. That took about four months of wrangling with the franchise electric utility
11. The conduit for the electric and the separate conduit for the fiber have been run to the house and to the shop
12. The slab for the shop has been mostly formed up. There were some issues from the barn builder's work that really should have been done after the slab got poured but they were hard headed about not wanting to do it that way. They set the walk door too high. They had some of the trim for the garage door openings extending into the concrete, and had it nailed to wood blocks attached to the posts, which would be in the concrete. It's taken a bit of back and forth with them to get it fixed and Sean and I had to do quite a bit of it last Saturday. We're just trying to make it work.

I think that's most of it. Work has been very busy. Working on the new house build is like a part time job itself.

Sean (my brother) and I basically finished up the 14-month restoration of Dad's garage in early September. We've been working on our home in Spring every weekend since. We've pressure washed the wood privacy fence, the back patio, the driveway, the sidewalk, the curb and the front walk. We've done some minor fence repair. We've replaced a light fixture in the Master bedroom closet. We fabricated some stainless trim to cover the gaps between the stonework for the outdoor kitchen and the grill and side burner. On and on. We repaired a crack in the back patio (covered) and painted the back patio with some fancy concrete paint. We've had the house painted. We've had the trees trimmed. We're shining the place up like a new penny.

So between work, the new house build and polishing the old house. It's been really busy.

The cabinet walk-through for the new home is coming up, as is pouring the slab for the shop. Construction on the pool at the new place will start soon. The preconstruction meeting was supposed to take place today but got cancelled. Anyway, there's been a lot going on. Here's some pics....

IMG_20241102_153904.jpg
IMG_20241102_153902.jpg
20241026_091257.jpg
IMG_20241102_153852.jpg
IMG_20241102_153912.jpg
IMG_20241102_153909.jpg
IMG_20241102_153925.jpg
IMG_20241102_153924.jpg
IMG_20241102_153927.jpg
IMG_20241102_153916.jpg
IMG_20241102_153908.jpg
20241020_124219.jpg
20241012_140511.jpg
20241026_085146.jpg
20241102_105622.jpg
20241026_090542.jpg
20241020_131504.jpg
 
Last edited:
No, that's just the fastest two months of my life. The barn doesn't look much different. I was probably waiting until the slab got poured but the house has been going full speed ahead.
1. Framing is done
2. The roof is decked
3. The cornicing is done
4. All windows and doors are installed
5. The plumbing/electrical/HVAC rough in is done
6. The roof is mostly shingled
7. The brick and stone is mostly done
8. The spray foam insulation has gone in
9. Sheetrock was being installed last Saturday, which was the last time I was out there
10. The power pole for our drop service has been installed. That took about four months of wrangling with the franchise electric utility
11. The conduit for the electric and the separate conduit for the fiber have been run to the house and to the shop
12. The slab for the shop has been mostly formed up. There were some issues from the barn builder's work that really should have been done after the slab got poured but they were hard headed about not wanting to do it that way. They set the walk door too high. They had some of the trim for the garage door openings extending into the concrete, and had it nailed to wood blocks attached to the posts, which would be in the concrete. It's taken a bit of back and forth with them to get it fixed and Sean and I had to do quite a bit of it last Saturday. We're just trying to make it work.

I think that's most of it. Work has been very busy. Working on the new house build is like a part time job itself.

Sean (my brother) and I basically finished up the 14-month restoration of Dad's garage in early September. We've been working on our home in Spring every weekend since. We've pressure washed the wood privacy fence, the back patio, the driveway, the sidewalk, the curb and the front walk. We've done some minor fence repair. We've replaced a light fixture in the Master bedroom closet. We fabricated some stainless trim to cover the gaps between the stonework for the outdoor kitchen and the grill and side burner. On and on. We repaired a crack in the back patio (covered) and painted the back patio with some fancy concrete paint. We've had the house painted. We've had the trees trimmed. We're shining the place up like a new penny.

So between work, the new house build and polishing the old house. It's been really busy.

The cabinet walk-through for the new home is coming up, as is pouring the slab for the shop. Construction on the pool at the new place will start soon. The preconstruction meeting was supposed to take place today but got cancelled. Anyway, there's been a lot going on. Here's some pics....

View attachment 248110View attachment 248111View attachment 248112View attachment 248113View attachment 248114View attachment 248115View attachment 248116View attachment 248117View attachment 248118View attachment 248119View attachment 248120View attachment 248121View attachment 248122View attachment 248123View attachment 248124View attachment 248125View attachment 248126
You sure you can fit 8 cars in the shop? Looks good man! Probably have told the power company you want solar panels to help power them they might have been faster?
 
The 2025 Calendars are HERE. Two different editions, two different sizes, and a digital package!! Starting at $12.97US

GBodyForum is a participant in the Amazon Services LLC Associates Program, an affiliate advertising program designed to provide a means for sites to earn advertising fees by advertising and linking to amazon.com. Amazon, the Amazon logo, AmazonSupply, and the AmazonSupply logo are trademarks of Amazon.com, Inc. or its affiliates.

Please support GBodyForum Sponsors

Classic Truck Consoles Dixie Restoration Depot UMI Performance

Contact [email protected] for info on becoming a sponsor