What did you do to your shop today?

Yeah, my bench is a holy terror sometimes.

Hutch
 
So an update. Electrical 50% done. Office 80%. Putting outdoor kitchen on hold as to much going on and have to think it through as wife wants a bathroom out there too. Have 2 of 3 ceiling fans in. High bay LED lights on order. Cabinets in office planning to install this week, time permitting. Figuring out display shelves for office and stand up desk with background as I have to do zoom meetings. I had to do a deposition the other day from my home office and a few minutes in I saw my buck mount in the background. Oops. Cool mount but not professional. In this case I didn't care🙂
 
Finally got started on the foundation this week. The building supplier was supposed to do the foundation, but apparently decided it just wasn't worth their time. After several weeks of bugging them about when they were going to get started and being constantly told, "just give me a couple days and I'll get back to you" they FINALLY sent a guy (Frank) out to check the property etc. and he tells me, "We can start in a bout 2 weeks, just have 2 other jobs in front of you". I though great, we're finally going to get started. After about a week and a half, I give Frank a call back just to verify if they have a firm start date yet. He proceeds to tell me that he couldn't come to an agreement on price with the building supplier, so he's off the job, but he is willing to contract directly with me. So I'm pissed. Nobody has contacted me to tell me anything. I call the building supplier, leave several messages with the Project Manager even the CEO. I send email. Zero response

At this point, I'd been trying to get quotes directly from several local companies but nearly every single one of them flakes out. So I decided screw it, give Frank a call back and tell him to write up the contract and he'll start in a couple weeks.

So finally, this week, Frank shows up on site as promised and finally starts work on my foundation.

Stripping the top soil for the build area
View attachment 182484

Starting to lay down the gravel base
View attachment 182485

Gravel base built up and starting to excavate the perimeter footings
View attachment 182487

Central part compacted
View attachment 182488

He's being very meticulous with measuring heights and everything. Still has to finish compacting the trenches for the footings and the tapered section. Needs to build the forms, and carve out the base for a couple lateral beams. Then I get to lay the insulation and pex for the radiant heat and then he can do the rebar. Then inspection and finally pouring concrete. Maybe by the end of next week
Awesome
 
Finished up the forming, rebar, insulation and radiant tubing at the end of last week. Building inspector gave us the A-OK on Tuesday and have the pour booked for next week Tuesday. Will need to reposition some of the insulation just before the pour to try and minimize some of the gaps.

View attachment 183457
Share some pics after the slab is poured
 
So an update. Electrical 50% done. Office 80%. Putting outdoor kitchen on hold as to much going on and have to think it through as wife wants a bathroom out there too. Have 2 of 3 ceiling fans in. High bay LED lights on order. Cabinets in office planning to install this week, time permitting. Figuring out display shelves for office and stand up desk with background as I have to do zoom meetings. I had to do a deposition the other day from my home office and a few minutes in I saw my buck mount in the background. Oops. Cool mount but not professional. In this case I didn't care🙂
Let's see some pics of your progress!
 
Finished up the forming, rebar, insulation and radiant tubing at the end of last week. Building inspector gave us the A-OK on Tuesday and have the pour booked for next week Tuesday. Will need to reposition some of the insulation just before the pour to try and minimize some of the gaps.

View attachment 183457

Up until recently that wood probably cost more than the pour. Looking good. Are you planning for a future lift installation?
 
Picked up 5 wall cabinets from work. I started hanging them. Trying to do something with all the clutter in here. Right now it’s a complete disaster. Before this pic I was able to get 1.75 cars in here. Hopefully I’ll be able to get 2 in when I’m done.
 

Attachments

  • 5806EBE5-33BC-47A1-B3F0-D56DF2977476.jpeg
    5806EBE5-33BC-47A1-B3F0-D56DF2977476.jpeg
    370.3 KB · Views: 98
  • 5969F391-D9B2-44E9-BC4A-D8D44AA32A69.jpeg
    5969F391-D9B2-44E9-BC4A-D8D44AA32A69.jpeg
    375.6 KB · Views: 99
  • 8E14CE28-0CB0-4E4D-BF79-CB70C4BCFF72.jpeg
    8E14CE28-0CB0-4E4D-BF79-CB70C4BCFF72.jpeg
    403.5 KB · Views: 97

GBodyForum is a participant in the Amazon Services LLC Associates Program, an affiliate advertising program designed to provide a means for sites to earn advertising fees by advertising and linking to amazon.com. Amazon, the Amazon logo, AmazonSupply, and the AmazonSupply logo are trademarks of Amazon.com, Inc. or its affiliates.

Please support GBodyForum Sponsors

Classic Truck Consoles Dixie Restoration Depot UMI Performance

Contact [email protected] for info on becoming a sponsor